Winchester Center station
| Company type | MBTA Commuter Rail station |
|---|---|
| Industry | Public transportation |
| Founded | 1838 |
| Headquarters | Winchester, Massachusetts , United States |
| Products | Commuter rail services on the Lowell Line |
Winchester Center station serves as an MBTA Commuter Rail stop situated in Winchester, Massachusetts, operating on the Lowell Line. Positioned atop a viaduct in downtown Winchester, the station comprises two accessible side platforms alongside two tracks. Due to structural concerns, it was temporarily closed on January 8, 2021. A partial reopening took place on October 1, 2024, with full service expected to resume by June 2025.
Early history
The Boston and Lowell Railroad commenced service in 1835 and quickly introduced local stops.[1][2] By 1838, the station known as Woburn Gates—which was later renamed Winchester—was already operational.Cite error: The opening <ref> tag is malformed or has a bad name During the 1840s, the railroad began offering commuter connections to Boston.[1] Between 1903 and 1915, several proposals aimed at eliminating grade crossings in Winchester were considered, including plans to lower the tracks by and elevate the streets by .Cite error: The opening <ref> tag is malformed or has a bad name In 1942, bike racks were installed at the station to alleviate parking demand.Cite error: The opening <ref> tag is malformed or has a bad name
In the early 1950s, Boston and Maine Railroad (B&M) developed plans to elevate the tracks along both the New Hampshire Main Line and Woburn Branch through Winchester to remove downtown grade crossings.Cite error: The opening <ref> tag is malformed or has a bad name Construction began in 1955, culminating in the opening of new two-story brick stations at Wedgemere and Winchester Center in 1957.[2][3]
Until 1981, the Woburn Branch Railroad diverged just north of Winchester Center’s platforms; a short segment of this branch remains.[4]
Repair work
Since the completion of the viaduct in 1957, Winchester Center station had not undergone significant renovations. In September 2008, the MBTA approved a $1.4 million budget for repairs including platform and ramp refurbishment as well as upgrades to electrical systems and lighting.[5] This phase was completed by 2010, with additional renovation planned before the five-year lifespan of platform patches expired.[6]
On July 7, 2015, a hole discovered on the inbound platform necessitated closing the northern portion of that platform along with one ramp due to concrete deterioration. The remaining platform section and one ramp remained accessible. The MBTA intended to implement temporary repairs by the end of that year.[6] Further reinforcement work on platforms and ramps was carried out in 2017.[7]
Up until December 2020, certain Haverhill Line trains were routed via the Wildcat Branch and inner Lowell Line, stopping at Winchester Center.[8] This routing resumed in April 2021 but without intermediate station stops.[9]
Planning
The MBTA is undertaking station renovations aimed at repairing water damage and ensuring full accessible compliance. By December 2011, design progress had reached 15%, with Jacobs Engineering chosen for final design efforts in June 2012. However, funding delays postponed construction until 2013. Initial designs incorporating mini-high platforms failed to meet state accessibility requirements, prompting a shift toward full-length high-level platforms—a modification opposed by local authorities.
Following multiple revisions, a revised 15% design was completed in December 2015. The redesigned station will include -long high-level platforms, which are shorter than MBTA’s typical standard but sufficient for nine-car trains. A gauntlet track might be added to accommodate freight traffic from CSX Transportation. Additionally, a new interlocking south of the station is planned to improve operational flexibility and enable decommissioning of the former Woburn Branch interlocking north of the station after construction concludes. The design incorporates two redundant elevators at each platform’s southern end instead of demolishing the existing 1957 station for elevator installation. Ramps will be relocated or reconstructed around the nearby rotary with potential for future expansion.
Station design completion was anticipated by late 2016 with construction valued at $25.8 million scheduled for 2017. By October 2016, bidding was expected to commence that December. The MBTA allocated $34 million in 2016; however, projected costs increased to $54 million by 2018. By late 2019, estimates adjusted to $49.9 million—allocating $7.3 million for design and $42.5 million for construction. Construction was planned to start in fall 2020 with completion targeted for spring 2023 but faced delays due to budget impacts related to COVID-19.
Construction
The station was closed on January 8, 2021, due to deterioration of its structural components. Shortly after the closure, the MBTA restored funding for the project on January 11 and secured a demolition permit by January 25. The removal of the ramps was finalized by June 2021. In October 2021, a construction contract valued at $47.6 million was authorized, marking the commencement of a 28-month building period beginning in December 2021. Site work started in March 2022, with demolition of platforms and ramps proceeding through mid-2022, while utility installations continued into late 2022.
A ceremonial groundbreaking took place on June 30, 2022. By December 2022, construction progress had reached 25%, increasing to 30% by June 2023, with an anticipated completion date set for April 2024. Project setbacks were encountered due to plumbing code adherence issues, supply chain disruptions, and limited working hours during a service diversion from September to November 2023. As of November 2023, the station's construction was approximately 40% finished; the southern section—including 320 feet of each platform—was scheduled to open in July 2024, with the entire station expected to be operational by October. To facilitate ongoing work, midday weekday service reductions began on March 25, 2024.
In June 2024, the timeline was adjusted to allow a partial reopening in late September and full reopening by December. The initial segment was slated for September 30 but was postponed to October 1 due to elevator installation delays. By December 2024, about 80% of construction was complete. In early 2025, disagreements emerged between the town and MBTA concerning mitigation strategies and easement renewals. Midday service on the Lowell Line resumed on June 2, 2025; the remaining platforms opened the following day. A ribbon-cutting event was held on July 16.
Transit-oriented development initiatives as of 2024 include plans to replace surface parking lots owned by both the MBTA and the town along Waterfield Street’s southern side with a residential complex comprising 56 housing units.
- ↑ 1.0 1.1 Cite error: Invalid
<ref>tag; no text was provided for refs namedsne - ↑ 2.0 2.1 Cite error: Invalid
<ref>tag; no text was provided for refs named150years - ↑ Cite error: Invalid
<ref>tag; no text was provided for refs nameddepots - ↑ Cite error: Invalid
<ref>tag; no text was provided for refs namednetransit - ↑ ...
- ↑ 6.0 6.1 ...
- ↑ ...
- ↑ ...
- ↑ ...